Planned Outage in Tecumseh
Scheduled for Mar 07, 2023 8:57 AM
Outage Information |
Date | Mar 07, 2023 9:30 AM |
Customer(s) Affected | 24 |
Municipalities Affected | Tecumseh |
Location(s) within Affected Municipalities | ARBOUR ST, BEDELL ST, RENAUD ST |
Cause of Outage | Equipment breakage |
Actual Time of Restoration | Mar 07, 2023 14:40 |
Estimated Time of Restoration | Mar 07, 2023 14:00 |
Duration of Outage | 212 minutes |
Updates
Power Restored for Planned Outage in Tecumseh Mar 07, 2023 2:43 PM |
Additional Details | REPLACED POLE (P01812) THAT WAS DAMAGED IN ICE STORM |
Planned Outage in Tecumseh Mar 07, 2023 8:57 AM |
Additional Details | REPLACING POLE (P01812) THAT WAS DAMAGED IN ICE STORM |