Planned Outage in Leamington

Outage Information
DateJun 05, 2024 9:00 AM
Customer(s) Affected9
Municipalities AffectedLeamington
Location(s) within Affected MunicipalitiesSHAWNEE CRT
Cause of OutageDistributor activities
Actual Time of RestorationJun 06, 2024 15:05
Estimated Time of RestorationJun 06, 2024 15:00
Duration of Outage290 minutes

Updates

Planned Outage in Leamington
Jun 06, 2024 8:05 AM
Additional DetailsREPLACING TRANSFORMER AND PRIMARY CABLE
Planned Outage in Leamington
Jun 05, 2024 12:13 PM
Additional DetailsOUTAGE POSTPONED AND RESCHEDULED FOR JUNE 6. REPLACING TRANSFORMER AND PRIMARY CABLE
Planned Outage in Leamington
Jun 05, 2024 8:09 AM
Additional DetailsREPLACING TRANSFORMER AND PRIMARY CABLE