Unplanned Outage in Leamington

Outage Information
DateJan 23, 2025 8:15 PM
Customer(s) Affected28
Municipalities AffectedLeamington
Location(s) within Affected MunicipalitiesST, FOX ST, MARLBOROUGH ST W
Cause of OutageOH Secondary Cable
Actual Time of RestorationJan 23, 2025 21:00
Estimated Time of RestorationJan 23, 2025 22:00
Duration of Outage45 minutes

Updates

Power Restored for Unplanned Outage in Leamington
Jan 23, 2025 9:07 PM
Additional DetailsOUTAGE DUE TO DAMAGED SECONDARY CONDUCTOR. CREWS REPLACED SECONDARY AND RESTORED POWER.
Unplanned Outage in Leamington
Jan 23, 2025 8:24 PM
Additional DetailsOUTAGE DUE TO DAMAGED SECONDARY CONDUCTOR. CREWS WORKING TO REPLACE.