Skip to Main Content
Unplanned Outage in Leamington
Reported Jan 23, 2025 8:24 PM
Outage Information |
Date | Jan 23, 2025 8:15 PM |
Customer(s) Affected | 28 |
Municipalities Affected | Leamington |
Location(s) within Affected Municipalities | ST, FOX ST, MARLBOROUGH ST W |
Cause of Outage | OH Secondary Cable |
Actual Time of Restoration | Jan 23, 2025 21:00 |
Estimated Time of Restoration | Jan 23, 2025 22:00 |
Duration of Outage | 45 minutes |
Updates
Power Restored for Unplanned Outage in Leamington Jan 23, 2025 9:07 PM |
Additional Details | OUTAGE DUE TO DAMAGED SECONDARY CONDUCTOR. CREWS REPLACED SECONDARY AND RESTORED POWER. |
Unplanned Outage in Leamington Jan 23, 2025 8:24 PM |
Additional Details | OUTAGE DUE TO DAMAGED SECONDARY CONDUCTOR. CREWS WORKING TO REPLACE. |