Skip to Main Content
Unplanned Outage in Amherstburg
Reported Feb 22, 2025 9:12 AM
Outage Information |
Date | Feb 22, 2025 9:08 AM |
Customer(s) Affected | 3 |
Municipalities Affected | Amherstburg |
Location(s) within Affected Municipalities | SEYMOUR ST |
Cause of Outage | OH Transformer switch |
Actual Time of Restoration | Feb 22, 2025 10:25 |
Estimated Time of Restoration | Feb 22, 2025 12:00 |
Duration of Outage | 77 minutes |
Updates
Power Restored for Unplanned Outage in Amherstburg Feb 22, 2025 10:36 AM |
Additional Details | OUTAGE DUE TO BROKEN TRANSFORMER SWITCH. CREWS HAVE REPLACED SWITCH AND RESTORED POWER. |
Unplanned Outage in Amherstburg Feb 22, 2025 9:12 AM |
Additional Details | OUTAGE DUE TO BROKEN TRANSFORMER SWITCH. CREWS WORKING TO REPLACE SWITCH AND RESTORE POWER. |