Skip to Main Content
Planned Outage in Tecumseh
Scheduled for Oct 29, 2025 8:24 AM
| Outage Information |
| Date | Oct 29, 2025 9:00 AM |
| Customer(s) Affected | 11 |
| Municipalities Affected | Tecumseh |
| Location(s) within Affected Municipalities | COVE DR, MARINE DR |
| Cause of Outage | Distributor activities |
| Actual Time of Restoration | Oct 29, 2025 16:50 |
| Estimated Time of Restoration | Oct 29, 2025 16:00 |
| Duration of Outage | 443 minutes |
Updates
Power Restored for Planned Outage in Tecumseh Oct 29, 2025 7:57 PM |
| Additional Details | CREWS REPLACED TRANSFORMERS AND RESTORED POWER |
Planned Outage in Tecumseh Oct 29, 2025 3:00 PM |
| Additional Details | REPLACING TRANSFORMERS - ESTIMATED RESTORATION TIME HAS BEEN EXTENDED TO 4PM |
Planned Outage in Tecumseh Oct 29, 2025 8:24 AM |
| Additional Details | REPLACING TRANSFORMERS |