Skip to Main Content
Unplanned Outage in Tecumseh
Reported Nov 22, 2025 10:48 AM
| Outage Information |
| Date | Nov 22, 2025 8:07 AM |
| Customer(s) Affected | 3 |
| Municipalities Affected | Tecumseh |
| Location(s) within Affected Municipalities | LACASSE BLVD |
| Cause of Outage | OH Transformer |
| Actual Time of Restoration | Nov 22, 2025 16:27 |
| Estimated Time of Restoration | Nov 22, 2025 16:30 |
| Duration of Outage | 500 minutes |
Updates
Power Restored for Unplanned Outage in Tecumseh Nov 22, 2025 4:37 PM |
| Additional Details | REPLACED BLOWN TRANSFORMER |
Unplanned Outage in Tecumseh Nov 22, 2025 2:41 PM |
| Additional Details | CREWS CONTINUING WORK ON REPLACING BLOWN TRANSFORMER |
Unplanned Outage in Tecumseh Nov 22, 2025 10:48 AM |
| Additional Details | CREWS REPLACING BLOWN TRANSFORMER |