Unplanned Outage in Tecumseh

Outage Information#15870
DateAug 18, 2026 22:26
Customer(s) Affected4
Municipalities AffectedTecumseh
Location(s) within Affected MunicipalitiesST MARK'S RD
Cause of OutageBroken branch/tree growth/untrimmed tree
Actual Time of RestorationAug 19, 2026 01:28
Estimated Time of RestorationAug 19, 2026 01:00
Duration of Outage182 minutes

Updates

Power Restored for Unplanned Outage in Tecumseh
Aug 19, 2026 01:33
Additional DetailsPOWER HAS BEEN RESTORED
Unplanned Outage in Tecumseh
Aug 18, 2026 23:57
Additional DetailsOUTAGE TO REMOVE TREE BRANCH THAT FELL ONTO LINES. LINES WERE ALSO DAMAGED AND CREWS ARE WORKING TO REPLACE. ESTIMATED RESTORE TIME IS APPROX 1 HOUR.
Unplanned Outage in Tecumseh
Aug 18, 2026 22:28
Additional DetailsOUTAGE TO REMOVE TREE BRANCH THAT FELL ONTO LINES