Planned Outage in Tecumseh

Outage Information
DateOct 08, 2020 9:29 AM
Customer(s) Affected42
Municipalities AffectedTecumseh
Location(s) within Affected MunicipalitiesCOLLIER CRES, HARBOURNE CRES
Cause of OutageScheduled Outage
Actual Time of RestorationOct 08, 2020 11:29 AM
Estimated Time of RestorationOct 08, 2020 4:00 PM
Duration of Outage120 minutes

Updates

Power Restored for Planned Outage in Tecumseh
Oct 08, 2020 12:08 PM
Additional DetailsTRANSFORMER (TX10023) WAS REMOVED FROM SERVICE AND REPLACED WITH A SECONDARY SERVICE PED (PD1S024)
Planned Outage in Tecumseh
Oct 08, 2020 8:17 AM
Additional DetailsTRANSFORMER (TX10023) IS BEING REMOVED FROM SERVICE AND REPLACED WITH A SECONDARY SERVICE PED (PD1S024)