Planned Outage in Tecumseh

Outage Information
DateJun 10, 2021 9:00 AM
Customer(s) Affected9
Municipalities AffectedTecumseh
Location(s) within Affected MunicipalitiesGAUTHIER DR, LESPERANCE RD
Cause of OutageScheduled Outage
Actual Time of RestorationJun 10, 2021 2:54 PM
Estimated Time of RestorationJun 10, 2021 4:00 PM
Duration of Outage354 minutes

Updates

Power Restored for Planned Outage in Tecumseh
Jun 10, 2021 3:51 PM
Additional DetailsREPLACED TRANSFORMER (TX10115) WITH NEW TRANSFORMER (TX1P115)
Planned Outage in Tecumseh
Jun 10, 2021 8:06 AM
Additional DetailsREPLACING TRANSFORMER (TX10115) WITH NEW TRANSFORMER (TX1P115)