Unplanned Outage in Tecumseh
Reported Feb 13, 2026 11:26 AM
Outage Information
Date
Feb 13, 2026 2:00 PM
Customer(s) Affected
139
Municipalities Affected
Tecumseh
Location(s) within Affected Municipalities
COMMUNITY CRES, HEATHERGLEN DR, LANOUE ST, RENAUD ST, RYEGATE DR
Cause of Outage
Distributor activities
Actual Time of Restoration
Feb 13, 2026 16:40
Estimated Time of Restoration
Feb 13, 2026 16:30
Duration of Outage
17 minutes
Updates
Power Restored for Unplanned Outage in Tecumseh Feb 13, 2026 5:05 PM
Additional Details
OUTAGE REQUIRED TO RESTORE SWITCHING TO NORMAL CONFIGURATION AFTER TRANSFORMER REPLACEMENT IS COMPLETE
Unplanned Outage in Tecumseh Feb 13, 2026 3:21 PM
Additional Details
OUTAGE HAS BEEN DELAYED TO 3:30PM DUE TO DELAYS IN THE FIELD. OUTAGE REQUIRED TO RESTORE SWITCHING TO NORMAL CONFIGURATION AFTER TRANSFORMER REPLACEMENT IS COMPLETE
Unplanned Outage in Tecumseh Feb 13, 2026 11:26 AM
Additional Details
OUTAGE REQUIRED TO RESTORE SWITCHING TO NORMAL CONFIGURATION AFTER TRANSFORMER REPLACEMENT IS COMPLETE