Unplanned Outage in Leamington

Outage Information
DateDec 15, 2024 8:00 AM
Customer(s) Affected1
Municipalities AffectedLeamington
Location(s) within Affected MunicipalitiesALEXIA CRT, AUDREY ST, AUGUSTA DR, BABKIRK LANE, BAYVIEW PLACE, BRUCE AVE, CHEROKEE LANE, CHERRY LANE, CHERRYWOOD AVE, CHEYENNE CRT, CLAIRE ST, CONOVER AVE, CORONATION AVE, COUNTESS ST, CYPRESS POINTE, DESERT SPRINGS CRES, DESTINY DR, DONALD AVE, ERIE GLEN CRES, ERIE ST S, FOREST AVE, FOSTER AVE, FRANKLIN RD, GOLD COAST, HENRY AVE, JANE ST, LORNE AVE, MALIBU DR, MARGARET ST, MARLENE CRES, MCGAW ST, MELROSE AVE, NAVAJO COURT, NAVAJO CRT, ORCHARD HEIGHTS AVE, PARK ST, PARKDALE AVE, PARKDALE PLACE, PEBBLE BEACH CRT, PINEHURST AVE, PULFORD AVE, QUEENS HILL CRES, RICKWAY DR, ROBSON RD, SEACLIFF DR E, SEACLIFF DR W, SHAWNEE CRT, SHERK ST, ST ANDREWS CRT, STEWART CRES, TANGLEWOOD DR
Cause of OutageAdverse Environment (2023)
Actual Time of RestorationDec 15, 2024 14:30
Estimated Time of RestorationDec 15, 2024 14:00
Duration of Outage390 minutes

Updates

Power Restored for Unplanned Outage in Leamington
Dec 15, 2024 2:34 PM
Additional DetailsCREWS HAVE REPLACED DAMAGED TRANSFORMER AND RESTORED POWER TO ALL REMAINING CUSTOMERS
Unplanned Outage in Leamington
Dec 15, 2024 1:06 PM
Additional DetailsOUTAGE DUE TO POLE FIRE CAUSED BY BLOWN TRANSFORMER. CREWS WERE ABLE TO ISOLATE AND PARTIALLY RESTORE POWER. CREWS CURRENTLY WORKING TO REPLACE TRANSFORMER. APPROXIMATELY 5 CUSTOMERS STILL WITHOUT POWER.
Unplanned Outage in Leamington
Dec 15, 2024 9:15 AM
Additional DetailsOUTAGE DUE TO POLE FIRE CAUSED BY BLOWN TRANSFORMER. CREWS WERE ABLE TO ISOLATE AND PARTIALLY RESTORE POWER. APPROXIMATELY 75 CUSTOMERS ARE STILL WITHOUT POWER.
Unplanned Outage in Leamington
Dec 15, 2024 8:09 AM
Additional DetailsCAUSE UNKNOWN, CREWS HAVE BEEN DISPATCHED