Unplanned Outage in Leamington

Outage Information
DateApr 29, 2025 4:12 AM
Customer(s) Affected14
Municipalities AffectedLeamington
Location(s) within Affected MunicipalitiesMARLENE CRES, DONALD AVE
Cause of OutageWildlife
Actual Time of RestorationApr 29, 2025 07:40
Estimated Time of RestorationApr 29, 2025 08:00
Duration of Outage208 minutes

Updates

Power Restored for Unplanned Outage in Leamington
Apr 29, 2025 7:55 AM
Additional DetailsOUTAGE DUE TO ANIMAL CONTACT. CREWS REPLACED BLOWN TRANSFORMER FUSE AND RESTORED POWER.
Unplanned Outage in Leamington
Apr 29, 2025 6:15 AM
Additional DetailsCAUSE UNKNOWN, CREWS HAVE BEEN DISPATCHED