Unplanned Outage in Leamington
Reported Apr 30, 2025 3:01 AM
Outage Information |
Date | Apr 30, 2025 2:42 AM |
Customer(s) Affected | 23 |
Municipalities Affected | Leamington |
Location(s) within Affected Municipalities | ERIE ST N, QUEENS AVE, WILKINSON DR, WINDSOR AVE |
Cause of Outage | Adverse Environment (2023) |
Actual Time of Restoration | Apr 30, 2025 05:28 |
Estimated Time of Restoration | Apr 30, 2025 07:00 |
Duration of Outage | 166 minutes |
Updates
Power Restored for Unplanned Outage in Leamington Apr 30, 2025 5:35 AM |
Additional Details | OUTAGE DUE TO POLE FIRE. CREWS REPLACED POLE AND RESTORED POWER |
Unplanned Outage in Leamington Apr 30, 2025 3:01 AM |
Additional Details | OUTAGE DUE TO POLE FIRE. CREWS OPENED SWITCH TO ISOLATE POLE |