Unplanned Outage in Tecumseh

Outage Information
DateJun 15, 2025 2:30 PM
Customer(s) Affected8
Municipalities AffectedTecumseh
Location(s) within Affected MunicipalitiesLESPERANCE RD, MCNORTON ST
Cause of OutageUG Secondary Cable
Actual Time of RestorationJun 15, 2025 15:50
Estimated Time of RestorationUnknown
Duration of Outage80 minutes

Updates

Power Restored for Unplanned Outage in Tecumseh
Jun 15, 2025 4:09 PM
Additional DetailsBLOWN TRANSFORMER FUSE DUE TO BAD UNDERGROUND CONDUCTOR. CREWS REPLACED FUSE AND CONDUCTED SWITCHING TO ISOLATE BAD CONDUCTOR AND RESTORE POWER.
Unplanned Outage in Tecumseh
Jun 15, 2025 3:57 PM
Additional DetailsBLOWN TRANSFORMER FUSE DUE TO BAD UNDERGROUND CONDUCTOR.