Unplanned Outage in Tecumseh

Outage Information
DateJun 16, 2025 9:30 AM
Customer(s) Affected8
Municipalities AffectedTecumseh
Location(s) within Affected MunicipalitiesLESPERANCE RD, MCNORTON ST
Cause of OutageUG Transformer
Actual Time of RestorationJun 16, 2025 21:30
Estimated Time of RestorationJun 16, 2025 23:00
Duration of Outage720 minutes

Updates

Power Restored for Unplanned Outage in Tecumseh
Jun 16, 2025 9:36 PM
Additional DetailsREPLACING DEFECTIVE TRANSFORMER AND PULLING IN NEW UNDERGROUND PRIMARY CABLE
Unplanned Outage in Tecumseh
Jun 16, 2025 2:25 PM
Additional DetailsESTIMATED RESTORE TIME HAS BEEN DELAYED AS THE CREW ALSO HAS TO PULL IN NEW UNDERGROUND PRIMARY CABLE. REPLACING DEFECTIVE TRANSFORMER
Unplanned Outage in Tecumseh
Jun 16, 2025 9:38 AM
Additional DetailsREPLACING DEFECTIVE TRANSFORMER