Unplanned Outage in Leamington
Reported Apr 05, 2026 21:12
| Outage Information |
| Date | Apr 05, 2026 21:02 |
| Customer(s) Affected | 19 |
| Municipalities Affected | Leamington |
| Location(s) within Affected Municipalities | FULLER AVE, GRACE AVE, KIMBALL AVE, NANCY AVE, TALBOT ST W |
| Cause of Outage | Unknown |
| Actual Time of Restoration | Apr 05, 2026 22:22 |
| Estimated Time of Restoration | Apr 05, 2026 23:00 |
| Duration of Outage | 80 minutes |
Updates
Power Restored for Unplanned Outage in Leamington Apr 05, 2026 22:25 |
| Additional Details | CREWS REPLACED BLOWN TRANSFORMER FUSE AND RESTORED POWER. CAUSE COULD NOT BE DETERMINED. |
Unplanned Outage in Leamington Apr 05, 2026 21:12 |
| Additional Details | BLOWN TRANSFORMER FUSE, CAUSE UNKNOWN. CREWS HAVE BEEN DISPATCHED. |