Skip to Main Content
Unplanned Outage in Tecumseh
Reported Aug 09, 2026 19:10
| Outage Information | #15824 |
| Date | Aug 09, 2026 18:54 |
| Customer(s) Affected | 5 |
| Municipalities Affected | Tecumseh |
| Location(s) within Affected Municipalities | CLARICE AVE |
| Cause of Outage | Unknown |
| Actual Time of Restoration | Aug 09, 2026 20:56 |
| Estimated Time of Restoration | Unknown |
| Duration of Outage | 122 minutes |
Updates
Power Restored for Unplanned Outage in Tecumseh Aug 09, 2026 21:00 |
| Additional Details | OUTAGE DUE TO BLOWN TRANSFORMER FUSE. CREWS PATROLED LINES BUT COULD NOT DETERMINE CAUSE. CREWS REPLACED FUSE AND RESTORED POWER. |
Unplanned Outage in Tecumseh Aug 09, 2026 19:10 |
| Additional Details | CREWS ARE INVESTIGATING |