Unplanned Outage in Tecumseh

Outage Information#15824
DateAug 09, 2026 18:54
Customer(s) Affected5
Municipalities AffectedTecumseh
Location(s) within Affected MunicipalitiesCLARICE AVE
Cause of OutageUnknown
Actual Time of RestorationAug 09, 2026 20:56
Estimated Time of RestorationUnknown
Duration of Outage122 minutes

Updates

Power Restored for Unplanned Outage in Tecumseh
Aug 09, 2026 21:00
Additional DetailsOUTAGE DUE TO BLOWN TRANSFORMER FUSE. CREWS PATROLED LINES BUT COULD NOT DETERMINE CAUSE. CREWS REPLACED FUSE AND RESTORED POWER.
Unplanned Outage in Tecumseh
Aug 09, 2026 19:10
Additional DetailsCREWS ARE INVESTIGATING